Meeting - Do you update your tasks before the Daily Scrum?

Updated by Hajir Lesani [SSW] 5 months ago. See history

123
<introEmbed body={<> All team members must update their tasks with status, (and remaining hours if you are estimating tasks) prior to the daily Scrum meeting. </>} />
Image

Figure: Update your tasks to keep the burn-down rate accurate

Note: If you are updating the details of a PBI then follow the rule Do you know when you use @ mentions in a PBI?


Learn more about the meetings in Scrum:

Tip: It can be helpful to finish the Sprint Planning meeting with the first Daily Scrum of that Sprint.


Scrum at Microsoft Videos

Short Version (3:48)

Long Version (12:15)